Initial aftercare for completed construction works
The soft landings framework is a joint initiative between BSRIA (Building Services Research and Information Association) and UBT (Usable Buildings Trust). It is an open-source framework that is intended to ‘…smooth the transition into use and to address problems that post-occupancy evaluations (POEs) show to be widespread’ (ref Useable Buildings Trust).
The government considers that soft landings sits alongside Building Information Modelling (BIM), as BIM feeds facility management systems and helps enable future alterations to completed buildings. As a result, it is thought that in parallel to the roll out of BIM, the government may mandate a Government Soft Landings (GSL) handover protocol for central government projects by 2016.
Soft landings includes provisions for initial aftercare and extended aftercare services for three years after the completed development has been handed over for occupation. A decision to require this aftercare should be made early during the development of the project so that the necessary services can be included in tender documents and appointment agreements.
The initial aftercare period is intended to deal with immediate problems, help the occupants understand the development, and help facilities managers learn to operate it. This is a period of intensive aftercare that will typically last 4 to 6 weeks, but may be longer for complex buildings such as hospitals and shorter for simple buildings such as shops. After this, the aftercare on site will reduce, although periodic reviews will continue.
A visible and accessible soft landings team, including members of the design and construction team, should be stationed on site to receive feedback, fine tune systems and ensure proper operation of the completed development. The architect will often be the main point of contact for occupants during this period, although queries most commonly relate to the operation of building services systems, and so the they will need good access to other members of the project team.
Aftercare meetings may be held with building users to explain how the building operates, answer questions and obtain feedback. The aftercare team may also disseminate information about problems that have been encountered, and progress that has been made, perhaps by issuing fortnightly newsletters.
There may be regular ‘walkabouts’ to assess operational performance and obtain data, and there will be specific meetings with facilities managers to explain systems operation in detail and obtain feedback.
This process also provides the opportunity for the project team to learn about problems that have been encountered, assess what steps might be taken to rectify them and consider how to avoid them on future projects.
The initial aftercare period will be followed by extended aftercare during years 1-3, when outstanding issues are resolved and post occupancy evaluations are fed-back for future projects. In year 1, problems are identified, training provided and systems fine-tuned, with regular reviews. In years 2 and 3, performance is reviewed, and post occupancy surveys carried out, but with reviews becoming less frequent.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- BIM and facilities management.
- BREEAM Aftercare support.
- Building information modelling.
- Building log book.
- Building owner's manual.
- Building users guide.
- Building performance metrics.
- Client commissioning.
- Defects liability period.
- Extended aftercare.
- Government construction strategy.
- Handover to client.
- Lessons learned report.
- Medical Research Council Laboratory of Molecular Biology soft landings project.
- Migration strategy.
- Occupation of completed construction site.
- PAS 1192-2:2013
- Post occupancy evaluation.
- Post project review.
- Performance in use.
- Snagging.
- Soft landings.
- Soft Landings for owners.
- Technical guide.
Featured articles and news
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
ECA launches Welsh Election Manifesto
ECA calls on political parties 100 day milestone to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.